Committed delivery date


Thecommitted delivery date is the delivery date the supplier confirms for a purchase order. It replaces the originally requested date and becomes the valid reference for planning and for measuring on-time performance.

Its value depends on being current. A date committed when the order is issued and never revalidated is as useful as no date at all: projects and maintenance work are scheduled around it, and the slip is discovered only when the material fails to arrive. Every rescheduling should be logged with its reason and the date the supplier gave notice, because a supplier's rescheduling pattern says more about it than the final delay.

It is also the right denominator for measuring on-time performance: comparing receipt against the original date measures the error in the initial estimate, not the supplier's performance.

In Verdana: a complete history of the original date and every rescheduling, each with its reason.